Kitchen Remodel Order of Operations: What Comes First, Step by Step
Cabinets, countertops, backsplash, floor, paint and trim each wait on the step before them. We walk through our order of work, when to pick materials, whether the floor goes under the cabinets, and what moves the price in a Florida kitchen.

Kitchen Remodel Order of Operations: The Steps in Order
The kitchen remodel order of operations comes down to one rule: each part waits for the part it sits on or butts into. Get the order wrong and something gets cut twice, or a finished surface gets torn up to make room for the next one.
We are a family-owned company based in Bradenton, and this is the sequence we plan with homeowners. Our page on kitchen remodeling in Bradenton shows what each part covers: cabinets, countertops, backsplash tile, the floor, paint and trim.
- Plan and pick: measure the room, choose cabinets, stone, tile, floor and colors, and get it all on a written estimate.
- Tear out: cover what stays, then take out the old backsplash, countertops and cabinets, and the old floor if it is going.
- Prep: patch the walls, flatten what is under the floor, and paint the ceiling and open walls.
- Floor now, if it runs under the cabinets: tile goes in before any box is set.
- Cabinets: uppers and bases set level and square, then fastened to the wall.
- Countertops: measured off the cabinets that are really in the room, then set on them.
- Floor now, if it stops at the cabinets: a floating plank floor runs up to the cabinet bases.
- Backsplash: the tile is laid out, then set between the countertop and the uppers.
- Finish: baseboards, transitions at each doorway, the last coat of paint, the hardware, and the appliances back in place.
Other guides add a step after tear-out for work behind the walls, when the sink or the range moves to a new spot. We plan kitchens around where those already sit, so prep follows the tear-out.
Good to know
Only one step moves around: the floor. Where it lands depends on the floor you pick, and we decide it with you at the walkthrough.
The First Step: Planning and Picking Materials
Most of the hard choices in a kitchen happen before anything comes off the wall. At the free in-home walkthrough we measure the room with you, note where the sink, the range and the refrigerator sit, and talk about how you cook. Bring the sizes of the appliances you plan to keep or buy, so the cabinet run is drawn around them.
Then pick the big pieces early. Cabinets are often built or shipped to order, and the stone can't be cut until the cabinets are set. Those two choices can set your start date, so make them before the tear-out goes on the calendar.
What to decide before the tear-out
- Cabinet style, finish and hardware, and any drawers you want in place of shelves.
- The countertop stone, its edge, and where a seam can fall.
- The backsplash tile, its pattern and where it stops: at the uppers, the window, or the ceiling behind the hood.
- The floor: plank or tile, how far it runs, and whether it goes under the cabinets.
- Wall and ceiling colors that sit well with the cabinets and the stone.
Tear-Out: Old Cabinets, Countertops and Backsplash
Tear-out goes in a set order too. The floor gets covered first. Then the backsplash comes off the wall, the countertops lift off the boxes, and the cabinets come out one by one.

On one bungalow, the lower cabinets and countertops came out first, the wall below the uppers was stripped back, and plastic went down over the floor. That wall was closed up and patched smooth before the new base cabinets were set. A wall behind cabinets is easy to reach only once, so it gets fixed while it is bare.
What sits under the old cabinets tells us a lot. On a slab, we look for old tile, adhesive and low spots. On a raised wood floor, we check the subfloor under the sink base, where a slow leak can soften the wood. If the old floor is coming out too, the old floor removal and slab prep goes into your scope.
Does Flooring Go Under Kitchen Cabinets?
It depends on the floor, which is why guides online argue about it: both answers are right, for different floors. A floating floor, like click vinyl plank or laminate, should stop at the cabinets. Tile set in mortar can run under them.
Floating plank: cabinets first, then the floor
A click plank floor isn't fastened to the slab, so it needs room to move as the air changes. Cabinets set on top pin it in place, and plank makers warn that this can lead to buckling or joints that open up. So the cabinets go in first, and our luxury vinyl plank floors run up to the cabinet base with a small gap that the toe kick hides.
Tile: under the cabinets or around them
Tile can go either way. Running it under the cabinets means no cut line at the toe kick, less damage if an appliance leaks, and a finished floor if you ever change the layout. Stopping it at the cabinets uses less tile and keeps the new floor from serving as a workbench. Our page on tile floors covers how the slab is prepped first.
Two details matter more than people expect. The new floor should run into the dishwasher opening, so the dishwasher can slide out later without catching on a lip. And when the floor stops at the cabinets, its thickness comes out of the space under the counter, so we check that height before a thick floor is picked.
Still choosing between the two floors? Our comparison of tile vs LVP in a Florida home goes room by room, kitchen included.
Cabinets First, Then the Countertops
Cabinets are the frame for everything that follows. Floors and walls are seldom perfectly flat or plumb, so each box gets shimmed until it sits level, and the run is checked for square before it is fastened. Uppers often go up before the bases, so nothing is in the way while they are lifted.

On that bungalow, the base cabinets came in while the floor was still bare subfloor. The plank floor went down after them and runs up to the bases, the order a floating floor wants.
Replace kitchen cabinets and countertops together or apart?
Countertops are measured off the cabinets that are actually in the room, not off a drawing, because a shim here and there changes the numbers. Countertop suppliers ask for the cabinets to be installed before the final measure. So when you replace kitchen cabinets and countertops together, the new tops are cut for the new boxes.
Changing only the tops can work when the old boxes are sound and level. Keeping an old stone top on new cabinets is harder: it was cut for the old run, and lifting it off whole is never a sure thing. We check both at the walkthrough.
Backsplash Last: Laying Out a Herringbone
The backsplash goes on after the countertops because the tile has to fit the real space between the top and the uppers, and that space isn't fixed until the top is set. Tile it early and you are guessing. If the tile runs up to the hood or the uppers, those get hung first too.
On the bungalow, the herringbone backsplash was laid out on the new plank floor, next to a level, before the tile went on the wall. Laying it out dry shows where the points of the pattern land and how the cuts fall at the window and the ends of the run. Then the tile went up behind the range and the sink, with the floor covered.

Herringbone takes more cuts than a straight layout, and every cut piece at an edge has to look planned. Pick the pattern and where it stops before the tile is ordered, so the count covers the extra cuts. A straight or stacked layout reads calmer next to a busy stone.
Paint and Trim to Finish the Room
Paint comes in two passes. While the room is empty after tear-out, the ceiling and the open walls get painted, with nothing in the way and no new floor to protect. That matches how we plan interior painting: paint before the new floor whenever we can, for the reasons in our post on painting before or after new flooring. After the backsplash, the last coat goes on and the spots where cabinets and trim were fitted get touched up.
Trim closes the edges. New baseboards and trim go in after the floor, cut on site to the new floor height, with a transition at each doorway where the kitchen floor meets another floor. Hardware goes on last, once the paint is dry and the cabinet fronts are adjusted so the gaps between them are even.

Kitchens in Bradenton, Lakewood Ranch and Sarasota Homes
Most homes here sit on a concrete slab, since slab-on-grade building is the norm in Florida. A slab that dips makes cabinets harder to set level, so we look at it at the walkthrough. Older homes in Bradenton, like the early bungalows around the Village of the Arts, are a different case: the kitchen floor may sit on wood over joists or on an old slab, and we find out before anything is ordered.
Lakewood Ranch spans parts of Manatee and Sarasota counties, and new villages are still opening there. In a newer village, the kitchen often still has the cabinets, tops and backsplash the builder chose, and the layout may work as it is, so the order starts at the tear-out. Each village has its own association rules, so check work hours and where a dumpster can sit. Our page on kitchen remodeling in Lakewood Ranch covers those builder kitchens.
A condo kitchen adds steps before the first one. Many associations want the work approved in writing first, and some allow noisy work and elevator use for materials only in the off-season. If the floor changes too, read our guide to condo flooring and underlayment rules. For Sarasota homes and condos, see kitchen remodeling in Sarasota.
If your home sits empty part of the year, keep the air conditioning running through the job. Vinyl plank makers say not to install in an unconditioned room, and the UF/IFAS extension tips on indoor humidity (opens in a new tab) say the air conditioner or a dehumidifier keeps indoor moisture in check, and a smart thermostat lets you run it while you are away.
What Changes the Cost of a Kitchen Remodel in Florida
There is no fair single number for a kitchen, because the same room can be priced many ways. These are the choices that move the price of a kitchen remodel in Florida.
| What you choose | Why it moves the price |
|---|---|
| Cabinets | How many boxes, how they are built, the finish, and extras like drawers in place of shelves. |
| Countertop stone | The stone itself, how many slabs it takes, the edge, the seams and each cutout for a sink or cooktop. |
| Backsplash | The tile, the pattern and how high it runs. Herringbone takes more cuts than a straight layout. |
| Floor | Plank or tile, under the cabinets or around them, and how far it runs past the kitchen. |
| Tear-out and prep | What comes out, what is under it, and how much patching the walls and the floor need. |
| Paint and trim | Ceiling, walls, colors, new baseboards and the transitions at each doorway. |
| Access | Stairs, a condo elevator, building work hours and where materials can be stored. |
One habit keeps surprises down: make the big choices before tear-out, since a change after the cabinets are ordered costs more than a change on paper.
Ask for the estimate line by line. Ours lists what comes out, each material you picked, the scope and the full price, before any work starts. For the floor, our checklist of what a written flooring estimate should include shows what each line should say.
Common questions
What comes first in a kitchen remodel, cabinets or flooring?
That depends on the floor you choose. Click vinyl plank and laminate float, so they go down after the cabinets and stop at the cabinet base. Tile can go in first and run under the boxes. In both cases, run the floor into the dishwasher opening. We settle it at the walkthrough and put it on the estimate.
Does the backsplash go in before or after the countertops?
After. The countertops go on the cabinets first, and the backsplash tile is cut to fit the space between the top and the upper cabinets. Setting tile before the top means guessing that space, which can leave a gap or a row of tile to redo. If the backsplash runs up to the hood or the uppers, those go up before the tile as well.
Do you paint a kitchen before or after the cabinets go in?
Both, in two passes. The ceiling and the open walls get painted while the room is empty, before the cabinets and the new floor come in, so there are no new surfaces to mask off. After the backsplash and the trim are in, the walls get their last coat and the edges around the cabinets are touched up. The final coat is then the one nobody bumps.
What does a kitchen remodel include?
Ours covers the parts you see and use every day: the old cabinets, countertops and backsplash out; new cabinets set level; stone countertops; backsplash tile in the pattern you pick; hardware; a new plank or tile floor; paint; and baseboards and trim. Each part is its own line on your written estimate, and you can do one part on its own, like the backsplash or the floor.
How much does it cost to remodel a kitchen in Florida?
There is no fair number before someone sees the room. The price moves with the size of the kitchen, the cabinets and stone you choose, the backsplash pattern, how much comes out, whether the new floor runs past the kitchen, and access, like a condo elevator. We measure at a free in-home estimate and give you the full price in writing before work starts.
Free estimate
Get Your Kitchen's Order on Paper
Bring your wish list and the appliances you plan to keep. At a free in-home estimate we measure the kitchen, help you pick cabinets, stone and tile, and put the order and the price in writing before work starts.